Project Induced In Migration (PIIM) for the Tilenga Project

Project-induced in-migration (or influx) describes the movement of people into an area in anticipation of, or in response to, employment and other economic opportunities from the development and/or operation of a new project. Although the in-migration may result in improvements in infrastructure, services, and employment in the project area of influence, it can also lead to significant negative environmental, social and health impacts, adversely affecting both the project and the project-affected communities. Such impacts have the potential to fundamentally change the context in which a project operates, leading to significant consequences in terms of the planning, implementation, and outcomes of environmental, social and health programs and management plans, increased operational costs, and increased operational risk, ultimately affecting a project’s “social license to operate”.

As recognized by the ESIA, the Tilenga project PIIM is expected to have far reaching impacts on individuals, households, communities, public and private institutions, the physical environment and among other aspects. The impacts of PIIM and how they are effectively managed depends to a large extent on the pre-existing situation in the project area and the overall national and international social, economic, political, legal and human rights environment.

Eco and Partner Consult Ltd, was contracted by Total Energies EP Uganda to undertake Project Induced In Migration (PIIM) Studies for the Tilenga project, these studies constituted the following:

  • PIIM Planning and Scoping
  • Stakeholder Identification, Analysis and Engagement
  • PIIM Situation Analysis
  • Assessment of PIIM Risks and Impacts Mitigation
  • PIIM Strategy Development and Management Approaches
  • PIIM implementation; PIIM Management Plan

 

    COMPANY

    Plot No.16A Ntinda II Road,
    P.O. Box 23989, Kampala, Uganda
    +256 319291830


      Environmental and Social Impact Assessment for Food and beverage Processing Plant

      Location: Uganda


      Client: Harris International (U) Ltd

      Service: Environmental and social consultancy


      Food and beverage Processing Plant

      Hariss International Limited is one of Uganda’s leading manufacturers of food and beverages. Since its inception in 2005 the production of both food and beverages have been operating under the brand name RIHAM.

      Hariss International proposed to setup a new food and beverage processing plant in Kireku Zone, Mukono District in 2011.
      Eco & Partner provided Environmental and Social consultancy services to the developer, these included; Environmental Social Impact Assessment for the then proposed food and beverage Processing plant.

        COMPANY

        Plot No.16A Ntinda II Road,
        P.O. Box 23989, Kampala, Uganda
        +256 319291830


          Kingfisher Development Area

          Kingfisher Development Area

          Location: Kampala-Uganda
          Client: Uganda National Roads Authority

          Service: Environmental and social consultancy

          The Kingfisher Project is planned to develop the Kingfisher, Mputa, Nzizi and Waraga fields. The Project will produce 40,000 Barrels of Oil per day during peak production. The crude will be treated at a Central Processing Facility (CPF) located in the south-eastern shores of Lake Albert. The Kingfisher development wells will be highly deviated wells from onshore surface locations targeting the offshore reservoir.

          Eco & Partner has provided Environmental and Social Consultancy services to the developer encompassing the following:

          • Services for Environmental and Social Impact Assessment (ESIA)and Public Hearing for the Kingfisher ESIA Report. ESIA for development of the Kingfisher field in EA-3. Subsurface construction includes a total of 40 wells (27production wells and 13 injection wells); the surface construction will include well-pads, production flow lines and water injection flow lines, an oil export pipeline, a central processing facility, a lake water extraction station, camps, a jetty, an airstrip and roads
          • Invertebrates (Mud Snail) Baseline Investigation Study. The study was undertake based on IFC performance standard 6 requirements. This thought to verify presence of mud snails (an endangered species) in the near-shore habitats off the Buhuka Flats. The study area covered; the Bugoma Lagoon (33.2 ha), large bays (73.7 ha), open sandy shores (554.8 ha) and shallow river associated water (37.2 ha), totaling approximately 699 ha.
          • Critical species study at Kingfisher oilfield (Nahan Francolin, Grey Crown Crane, Eastern Chimpanzee)
          • Environmental Compliance Audit for CNOOC Uganda Facilities in Kingfisher Development Area, Transportation, Treatment and Disposal of Kingfisher drilling waste, Access Roads etc.

          Tilenga project

          Location: Uganda


          Client:TotalEnergies Exploration and Production Uganda Ltd

          Service: Environmental and social consultancy


          Tilenga project

          Tilenga: located in the Buliisa and Nwoya districts in the Lake Albert, the Tilenga project is operated by Total Energies (56.6%), in partnership with CNOOC and UNOC. It includes the development of six fields and the drilling of around 400 wells from 31 locations. Production will be delivered through buried pipelines to a treatment plant built in Kasenyi, for the separation and treatment of the fluids (oil, water, gas. All of the water produced will be reinjected into the fields and the gas will be used to produce the energy needed for the treatment process. Surplus electricity will be exported to the pipeline and the Ugandan grid.

          One of the fields developed is located inside Murchison Falls Park. The others are located outside the park, south of the Victoria Nile in sparsely populated rural areas and activities that are essentially agricultural.

          Eco & Partner has provided Environmental and Social Consultancy services to the developer encompassing the following:

          • Development of the Tilenga Project Environmental Social Impact Assessment. The various studies carried out during the preparation of the ESIA including: Air quality and climate change; noise and vibration; geology and soils; hydrogeology; surface water; landscape and visual; waste; Ecological and biological environment: Terrestrial vegetation; terrestrial wildlife; aquatic life; and Social-economic environment: archaeology and cultural heritage; health and safety; ecosystem services, Stakeholder engagement was performed as part of the social impact assessment. Unplanned events, cumulative impacts, and transboundary impacts were also assessed, in addition to providing an Environmental and Social Management Plan.
          • Health Safety and Environment Compliance Auditing for the Tilenga Project Facilities and Activities including well pads, Airstrip’s, camps, Industrial Area, Access Roads etc.
          • Environment Monitoring of the project Activities and Facilities.
          • Social performance through provision of Transitional Support (Distribution of Dry Rations) for RAP 2-5.
          • Eco-toxicological studies for plants around Purongo Waste Consolidation Area.
          • Environmental and Social Impact Assessment for additional Project Components and facilities including the Nile Crossing, Tilenga Additional Borrow Pits, and Workers Camps.
          • Tilenga Project Human Rights Impact Assessment.
          • Tilenga Project Induced In-Migration (Influx Studies).

            COMPANY

            Plot No.16A Ntinda II Road,
            P.O. Box 23989, Kampala, Uganda
            +256 319291830


              Environmental Compliance Auditing for the Critical Oil Roads

              Environmental Compliance Auditing for the Critical Oil Roads

              Location: Uganda


              Client: Uganda National Roads Authority

              Service: Environmental and social consultancy


              UNRA has a mandate to develop and maintain the national roads network, advise Government on general roads policy and contribute to addressing of transport concerns.

              Eco has provided environmental and social consultancy services including but not limited to:
              Environmental and Social Compliance Auditing of various projects implemented by the developer:
              ⦁ Masindi (Kisinja) – Park Junction and Tangi Junction – Para – Buliisa (159 Km).
              ⦁ Para Bridge, which is composed of 13 spans each at 40m and bridge deck of 15.95m wide.
              ⦁ The Buhimba-Nalweyo-Bulamagi and Bulamagi-Igayaza-Kakumiro roads (93km)

                COMPANY

                Plot No.16A Ntinda II Road,
                P.O. Box 23989, Kampala, Uganda
                +256 319291830